Middlewood Plaza – Construction Update – August 2019

Middlewood Plaza: Foundations completed

Since our last update the foundation works have been entirely completed, with the formation of the basement walls now undergoing finishing touches. Drainage connections have also been installed in Cow Lane (situated directly behind the development) ahead of the programme.

 

Middlewood Plaza: Next steps

Works are now progressing to form temporary ramps from the street level of the development down into the basement, which will allow cranes to enter in advance of the erection of the structural steel frame in late August.

The frame itself is being manufactured in the works of Leach Structural Steelwork LTD, who will be erecting the frame on site throughout September and October.