Hadrian’s Tower – Construction Update – August 2019

Since our last update, the concrete frame of the tower has now been poured to level 25, with works to level 26 in progress.

The bathroom pods have been delivered and lifted up to level 16; with levels 2-10 being fitted into their final positions and levels 11-16 in progress.

The Façade unitised glazing system is now completed up to level 3, with brackets and fixings fitted up to level 5 and the fixings fitted up to level 12 – this is a key step in preparing for the unitised glazing to be fully installed.

The brickwork piers and feature lintels are progressing to level 5, with internal partitioning having commenced from levels 2 to 7. Finally, the first fix M&E services are substantially completed between levels 2, to 5 and are progressing upwards.